As crane cable supports structural steel wide flange column section, structural ironworker inserts tapered end of bull pin into bolt holes in lower end of suspended column section and splice plate bolted to top of previously erected column section to hold, support the column section in position to splice it to top of column below.This adds to the support already provided by two inserted spud wrenches. The steel cable on lower column section is part of tensioned cable temporary diagonal bracing that supports the steel frame against lateral/ side loads until all connections have been completed. Ashley Terrace, Ann Arbor, Michigan April, 2007.